Nigeria’s power supply may see a boost as eight out of the 10 National Integrated Power Project (NIPP) electricity generation plants under construction have now been completed and are ready to generate 2,000 megawatts of power to the national grid.
The plants, which have seen their completion dates deferred before, are set to commence, according to a statement issued by the Niger Delta Power Holding Company (NDPHC), operators of the NIPP.
The completed plants include the 750mw Omotosho II in Ondo State, 450mw Ihovbor Plant in Edo State, 750mw Olorunsogo II in Ogun State, 450mw Sapele Plant in Delta State, 434mw Geregu II in Kogi State, 450mw Alaoji Plant in Abia State, 563mw Calabar Plant in Cross River State, and the 235mw Gbarain Plant in Bayelsa State.
According to NDPHC, “These power plants, along with associated gas transmission metering/receiving infrastructure projects, have been inaugurated and connected.
“Also, the Afam Thermal Power Plant in Port Harcourt, Rivers State, is expected before December this year, to deliver 340mw of electricity to the National Grid, with assurance of availability of gas.’
Babatunde Fashola, minister of power, works and housing, disclosed this in Afam in the Oyigbo Local Government Area of Rivers State at the weekend, adding that with the work on the 240MW capacity Afam III Plant at an advanced stage and the burnt transformer for the 100MW Afam 1V now repaired, the two should deliver a combined 340MW of energy to the grid before the end of the year, subject to the availability of sufficient gas to fire them.
“All of the turbines and equipment needed for the completion of Afam III are already in the country, the only problems left included the provision of access roads and logistics, while the burnt transformer that would evacuate the 100MW from Afam 1V had been repaired and in good condition with the turbine,” Fashola said.
Fashola further said the government has been working at the Plants in the past 17 to 18 months to restore the place back to its optimum capacity, expressed delight at the progress of work assuring that before the end of the year, 340MW would be added to the National Grid from the facility. “That is part of our Incremental Power Initiative”, he said.
“What we have behind us is the Afam III and that is the Fast Power programme in collaboration with General Electric to restore 240MW to that place. All of the turbines and equipment needed for that project is already in Nigeria. So the only challenge we have now is roads, logistics and a few other problems; those are the things I have come to assess here,”
Noting that Afam 1V, “is the only surviving generation unit”, Fashola, who said the surviving Generation units 17 and 18 have a combined output of 100MW, added, however, that the power could not be evacuated due to the damaged transformer which, according to him, got burnt in January 2015.
“That was what was handed over to the Buhari government. So we have worked, we have restored and we have replaced the transformer and it is ready to go”, the Minister said adding, “We are here to assess the progress of the work that we have been doing here in the past 17 to 18 months to get this place back to its optimum capacity. But we now have issues with gas“.
On the steps taken by Government to solve the gas issue, the Minister, who said that the Buhari Government inherited a lot of debts owed to all the gas companies who, according to him, said they would no longer supply gas without payment, recalled that Government recently approved N701Billion under its Payment Assurance programme to ensure that henceforth all suppliers of gas to the nation’s power plants were paid.
“So we are telling Shell to let us separate the previous debt and create a programme to deal with it under the Central Bank of Nigeria programme”, adding, “And now that we have a Payment Assurance programme, we are assuring them that every gas they supply to this place now will be paid for”.
“We have already paid for power produced in January; we have got approval to pay for power produced in February because the bills come in arrears. So they are looking at that and they will come back to us; so hopefully we should add another 100MW to the grid from here (Afam 1V) very soon.”
For Afam V, which, he said, was the last one to be built, Fashola said the plant could not be maintained for four to five years after it was built resulting in so many things being damaged inside it adding that Government was now trying to get it into procurement and fix that.
Assuring that the project would be completed next year, the Minister added, “I think they both have 276MW combined; that is a lot of power again to the grid and that will happen over the next 12 to 15 or 16 months if we can start quickly”, pointing out that he was at the site to assess progress of work in order to deliver the project as soon as possible.
Responding to a question as to how soon the facility would be restored to optimum power delivery, the Minister declared, “As soon as the gas issue is sorted out, Afam 1V, with the capacity to deliver 100MW behind you as soon as we sort out the gas issues; it is the 240MW Afam III behind me if we meet our deadline, we want to finish before December; that will give you 340MW.”
“Then at the back there, Afam V, that is 276MW that will roll into next year; we can’t finish that this year. By December, we should get to 340MW; these are now engineering issues and time tabling and also, of course, continued peace. We have 100MW now that we can’t evacuate because there is no gas to fire it, we have fixed the problem, which was a burnt transformer. It has been repaired; the turbine is good, the transformer is good, now we have to go and get fuel to fire the car,” he said.
ISAAC ANYAOGU

